Rogers Centre – 1 Blue Jays Way, Toronto

Project Description

Complete retro-fit of 9 restaurants. This included complete demolition of all mechanical services, supply of new air handling units complete with all new chilled water, hot water piping, duct work grilles & diffusers, all new plumbing, gas piping, fire protection, insulation, controls, refurbishment of the existing ecology units, testing, and balancing. This was all completed in a three month period while the Rogers Centre was in business as usual: car show, Blue Jays home opener, etc. VR was required to work in change rooms and the main security offices with all custom made scaffolding. For security reasons VR installed cameras in some of these areas. The design and intent were being finalized as the project got on its way. VR played a very important part ensuring The Rogers Centre always had 6 of the 9 restaurants operational.